Wall supported in Makkah - Husseiniya

Description

Connecting between two walls, and separating between two different levels of ground, we made this great wall.

Implemented by bridging the dust behind it to reach the level of the upper ground, and to benefit from the area by pouring on phases:

The first phase: drill the holes in the base site every 40 cm where the iron bars have been installed using epoxy, for the aim to increase the stability of the wall base.

The second phase: install bars of 18 mm diameter and 3 m length every 25 cm, for the aim to increase the coherence between the wall and the base.

The third phase: pour the base, where the base has been designed as a dynamic width to reach the lowest point at 3 m because of the big height, which will increase the steadiness of the wall due to the weight of dust over the base.

The fourth phase: pour the wall on phases, as every 3 m because of the big height.

Time
:
2014
Client
:
 Mr. Ibrahim Al-Dosari, Mr. Abdullah Al Qubaisi
Status
:
Built
Group of Work
Architect Mohammad Assaf 
Eng. Mahmoud Sodan
Foreman Muhammad Isa
Foreman Mamdouh Mustafa

Consulting engineer Samir Assaf